Direct Answer
A full custom home checklist covers inquiry, job walk, due diligence,
plans, engineering, permitting, estimating, proposal review, production
handoff, site prep, foundation, framing, rough mechanicals, insulation,
drywall, finishes, punch list, final inspections, your walkthrough, and
closeout documentation. A checklist worth using accounts for both what
we’re doing and what you need to decide along the way.
Key Takeaways
- A real build checklist starts well before construction — don’t let
anyone tell you otherwise.
- Due diligence surfaces property, approval, and utility constraints
early, when they’re easiest to solve.
- Inspections should be baked into the sequence, not treated as an
afterthought.
- Long-lead items need tracking from day one.
- Your selections and anything you’re supplying yourself directly
affect the schedule.
- Closeout works best with visible punch-list and documentation
tracking.
Phase 1: Inquiry and Job Walk
Checklist:
- Define project goals.
- Discuss general budget expectations.
- Walk the property.
- Take photos.
- Gather measurements.
- Review sketches, drawings, or inspiration.
- Identify site access concerns.
- Note utilities, grading, drainage, or existing structure
considerations.
- Identify known HOA, DRC, ARC, or neighborhood requirements.
Phase 2: Due Diligence
Checklist:
- Confirm jurisdiction.
- Review zoning considerations.
- Review setbacks.
- Check for easements.
- Identify HOA or design-review requirements.
- Gather survey or site plan information.
- Review utility or septic constraints.
- Identify permit path.
- Identify open safety concerns.
- Clarify any required engineering or design documents.
Phase 3: Plans,
Engineering, and Estimate Package
Checklist:
- Prepare or collect drawings.
- Coordinate engineering where required.
- Define major scopes.
- Identify trade categories.
- Send bid packages to trades or vendors.
- Track bid follow-ups.
- Compare bids for missing scope, exclusions, and assumptions.
- Identify allowances.
- Identify owner-furnished items.
- Identify long-lead items.
- Clarify permit assumptions.
- Clarify schedule assumptions.
Phase 4:
Proposal Review and Production Handoff
Checklist:
- Review scope of work.
- Review exclusions.
- Review allowances.
- Review owner-supplied items.
- Review permit assumptions.
- Review schedule assumptions.
- Confirm selection deadlines.
- Confirm change order process.
- Approve proposal or agreement.
- Handle deposit or project-start requirements.
- Transition from estimating to production planning.
Phase 5: Mobilization and
Site Prep
Checklist:
- Confirm start date.
- Schedule utility locate.
- Confirm site access.
- Plan staging.
- Protect existing areas where applicable.
- Complete demolition if required.
- Complete layout.
- Prepare work area.
- Address temporary facilities or access needs.
Phase 6: Foundation and
Underground Work
Checklist:
- Excavation
- Forms
- Rebar
- Embeds
- Underground plumbing
- Underground electrical where applicable
- Compaction or testing requirements
- Pest pretreatment where applicable
- Required inspection
- Concrete placement
- Cure time
- Backfill
Phase 7: Framing and Dry-In
Checklist:
- Lumber delivery
- Truss delivery where applicable
- Wall framing
- Roof framing
- Sheathing
- Window and door openings
- Window and door installation or preparation
- Roofing or weather protection
- Framing inspection
Phase 8: Rough
Mechanical, Electrical, and Plumbing
Checklist:
- Rough plumbing
- Rough electrical
- HVAC rough-in
- Low voltage where applicable
- Fire blocking
- Rough inspections
- Corrections
Phase 9:
Insulation, Drywall, Texture, and Paint
Checklist:
- Insulation
- Inspection where required
- Drywall hang
- Drywall finish
- Texture
- Primer
- Paint
Phase 10: Interior and
Exterior Finishes
Checklist:
- Cabinets
- Countertops
- Appliances
- Tile or backsplash
- Trim
- Interior doors
- Flooring
- Finish plumbing
- Finish electrical
- HVAC trim-out
- Exterior lath, stucco, or paint where applicable
- Garage doors or specialty exterior items where applicable
Phase
11: Punch, Final Inspection, Walkthrough, and Closeout
Checklist:
- Create punch list.
- Complete corrections.
- Complete final clean.
- Complete smoke or safety checks where applicable.
- Complete utility activation where applicable.
- Complete final inspections.
- Conduct owner walkthrough.
- Provide closeout documentation.
- Provide warranty information where applicable.
Homeowner Decision Checklist
- Site goals
- Budget priorities
- Exterior materials
- Windows and doors
- Roofing
- Cabinets
- Counters
- Flooring
- Tile
- Plumbing fixtures
- Lighting
- Appliances
- Paint
- Hardware
- Owner-furnished items
- Change approvals
FAQ
What should be
done before construction starts?
Before we break ground, we should have scope, site due diligence,
drawings, engineering, permits, trade pricing, proposal review,
selections, and production handoff all squared away.
When do permits happen?
Timing depends on the project, jurisdiction, and required documents —
but permits are typically addressed before any work requiring approval
begins.
What happens before
foundation work?
We generally complete site prep, utility locate, layout, excavation
planning, and any documentation needed for inspections or concrete
work.
What is rough MEP?
Rough mechanical, electrical, and plumbing work — everything that
happens before the walls close up.
When are cabinets and
counters installed?
Cabinets typically go in before countertop templating and
installation, though exact timing depends on your project sequence and
material availability.
What is included in closeout?
Closeout can include punch-list completion, final inspections,
cleaning, your walkthrough, safety checks, documentation, and warranty
information.